Choir Chamber Construction and Pipe Organ Installation

After some structural issues and other unforeseen setbacks, construction on the choir chambers will begin Monday, April 13. The Construction portion of the project should take between 3 to 4 weeks, and the installation and tuning of the pipe organ approximately 2 months. During the construction phase, the choir loft will be closed and masked off to prevent construction debris. However, it is impossible to contain all of the dust, so adorers may want to sit towards the front of the church.

Thank you for your patience and join me in praying to St. Joseph the Worker and St. Cecilia that the last phase of our project stays on schedule.

Mark Powell
Pastoral Assistant for Administration